23 free practice questions on risk and control, Section D of the CIMA Advanced Management Accounting (P2) question bank. Topics include Expected value, TARA, Decision tree, Decision trees, TARA risk framework, Upside risk and opportunity management. Each question carries its syllabus reference and a worked explanation. Practise them in the quiz with instant feedback, or read every question with its answer further down this page.

→ Full P2 question bank and timed mock exam
→ P2 Common Mistakes
→ P2 Formula Sheet

Explanations shown after each answer. Skip freely. No time limit.
Section:
0
answered
0
correct
—
score
—
remaining
Question 1

Loading questions…

All 23 risk and control questions

The same questions the quiz above draws on, in syllabus order, each with its answer and worked explanation. 17 are multiple choice and 6 are numerical, where you work the answer out before choosing it.

Question 1 · Syllabus ref D1a · Expected value — decision under risk

A manager must choose between two options. Strategy A gives an 70% probability of generating £80,000 and a 30% probability of generating £20,000. Strategy B gives a certain outcome of £55,000. Based solely on expected monetary value, which option should be chosen?

  1. The second strategy, with a certain value of £55,000
  2. The first strategy, with an EV of £56,000
  3. Both strategies have equal expected monetary value
  4. The first strategy, with an EV of £62,000
Show answer and explanation

Answer: D. Expected value of Strategy A = (0.70 × £80,000) + (0.30 × £20,000) = £56,000 + £6,000 = £62,000. Since £62,000 > £55,000, The first strategy has the higher EV and should be chosen based on EMV alone. A common error is to weight the probabilities incorrectly — for example, 0.60 × £80,000 + 0.40 × £20,000 = £48,000 + £8,000 = £56,000, which would invert the comparison. EMV analysis does not incorporate risk preference; a risk-averse manager might still prefer the certain £55,000, but the pure EMV criterion points to the first strategy. The certain £55,000 is lower than £62,000, so it is not chosen on EMV alone, and the two values are not equal.

Question 2 · Syllabus ref D1a · Decision trees — rollback method

When using the rollback method to evaluate a decision tree, in what order are the calculations performed?

  1. Starting from the rightmost outcomes and working backwards, calculating expected values at chance nodes and taking the best option at decision nodes
  2. Starting from the leftmost decision node and working forwards, taking the highest-value branch at each stage
  3. Calculating every possible path's total value and selecting the one with the highest single outcome
  4. Ignoring probability-weighted calculations and selecting the strategy with the minimum possible loss at each stage
Show answer and explanation

Answer: A. The rollback method works from right to left — starting with the known outcomes at the ends of the branches, then working backwards through the tree. At chance nodes (circles), the expected value is calculated by probability-weighting the outcomes. At decision nodes (squares), the best option is selected (the highest EV branch), and other options are pruned. Working forwards from the initial decision would not be the rollback method; that is a forward pass used in different contexts. Selecting purely on highest single outcome ignores probability, and minimising the worst outcome is a maximin strategy, not the expected value rollback method.

Question 3 · Syllabus ref D1b · TARA risk framework

Which of the following correctly identifies all four risk responses in the TARA framework?

  1. Transfer, Analyse, Reduce, and Assess
  2. Transfer, Avoid, Reduce, and Accept
  3. Tolerate, Accept, Reduce, and Avoid
  4. Transfer, Avoid, Retain, and Assess
Show answer and explanation

Answer: B. The TARA framework identifies four possible risk responses: Transfer (pass the risk to a third party, e.g. through insurance), Avoid (eliminate the risk-creating activity), Reduce (take actions to lower the probability or impact of the risk), and Accept (consciously decide to live with the risk, often because the cost of other responses exceeds the benefit). The other options include plausible-sounding words but do not correctly name all four TARA responses — Analyse, Assess, Retain and Tolerate are not the correct TARA labels.

Question 4 · Syllabus ref D1b · TARA — choosing appropriate response

A company identifies a risk of flooding at a storage facility, which has a high potential impact but a low probability. The company decides to take out insurance against the financial loss. Which TARA response does this represent?

  1. Avoid — the company ceases the storage activity to remove the risk entirely
  2. Reduce — the probability of flooding is lowered through preventive measures
  3. Transfer — the financial consequences of the risk are passed to an insurer
  4. Accept — the company decides to do nothing and absorb any loss itself
Show answer and explanation

Answer: C. Taking out insurance passes the financial consequences of the risk to a third party (the insurer) in exchange for a premium — this is the defining feature of the Transfer response in TARA. Avoidance would require ceasing the storage activity altogether to eliminate the risk. Reduction would involve taking preventive measures to lower the probability or potential impact of flooding, such as building flood defences. Acceptance would mean consciously choosing to do nothing and bearing the cost of any flood loss directly, which is the opposite of paying for insurance.

Question 5 · Syllabus ref D1c · Upside risk and opportunity management

Which of the following best describes 'upside risk' in the context of risk management?

  1. Risk that can only ever be harmful and must always be reduced or transferred
  2. A technical term for very high-probability risks that are certain to occur
  3. Upside risk is not a recognised concept in formal risk management frameworks
  4. The possibility that outcomes could be better than expected, representing an opportunity that can be actively managed and pursued
Show answer and explanation

Answer: D. Upside risk refers to the possibility that outcomes could be better than expected — in other words, positive uncertainty or opportunity. Just as downside risk can be managed to limit harm, upside risk can be actively managed to maximise the chance of favourable outcomes. Risk management therefore encompasses both threat avoidance and opportunity pursuit, not just harm reduction. Upside risk is not inherently harmful (that is downside risk), and it is absolutely a recognised concept in formal risk management frameworks, including those used by professional accountants.

Question 6 · Syllabus ref D1d · Ethics and the public interest

Why are professional accountants expected to act in the public interest, rather than solely in the interests of their employer or client?

  1. Because the accounting profession's role in providing credible financial information underpins public trust in capital markets and the wider economy
  2. Because acting in the public interest always increases an employer's short-term profit
  3. Because regulatory requirements mandate that accountants prioritise public interest only in audit engagements
  4. Because the concept of public interest is purely aspirational and has no practical consequence for any real decision
Show answer and explanation

Answer: A. Professional accountants produce or assure financial information that market participants, investors, lenders and governments rely on to make decisions. If accountants were to act solely in client interests at the expense of accuracy, completeness or integrity, public trust in financial information would erode, undermining the functioning of capital markets and the broader economy. This is why the CIMA Code of Ethics requires accountants to act in the public interest as a fundamental principle. Acting ethically does not always maximise short-term employer profit, the public interest obligation extends beyond audit engagements, and it has very practical consequences — including professional sanctions — for real decisions.

Question 7 · Syllabus ref D1a · Sensitivity analysis vs EV

How does sensitivity analysis differ from expected value analysis in the way it handles uncertainty in a capital investment appraisal?

  1. They are identical techniques that always give the same result
  2. Sensitivity shows how much a variable can change before the decision reverses, without probabilities; EV weights outcomes by probability
  3. EV examines one variable at a time; sensitivity needs probability estimates for every outcome
  4. Sensitivity eliminates uncertainty by fixing all variables at their most likely value
Show answer and explanation

Answer: B. Sensitivity analysis examines how much a single key variable (such as sales volume, selling price or operating cost) can change before the NPV falls to zero, without assigning probabilities to different scenarios — it highlights which variables the decision is most sensitive to. Expected value analysis instead assigns probabilities to possible outcomes and calculates the probability-weighted average, giving a single expected outcome. The two techniques approach uncertainty differently and are not equivalent. The descriptions of which technique uses probability estimates are correctly stated here, and sensitivity analysis does not eliminate uncertainty — it maps its consequences.

Question 8 · Syllabus ref D1a · Expected value — payoff matrix

A manager must choose between two strategies. Strategy A: profit £150,000 if boom (probability 40%), £20,000 if recession (probability 60%). Strategy B: profit £80,000 if boom, £60,000 if recession (same probabilities). Which strategy has the higher expected monetary value?

  1. Strategy A with an EV of £72,000
  2. Strategy B with an EV of £68,000
  3. Both strategies have the same EV of £68,000
  4. Strategy A with an EV of £85,000
Show answer and explanation

Answer: A. EV of Strategy A = (0.40 × £150,000) + (0.60 × £20,000) = £60,000 + £12,000 = £72,000. EV of Strategy B = (0.40 × £80,000) + (0.60 × £60,000) = £32,000 + £36,000 = £68,000. Strategy A has the higher EV (£72,000 > £68,000) and would be selected under the pure EMV criterion. A risk-averse manager might still prefer Strategy B's lower variance. The £85,000 figure is a simple average of Strategy A's outcomes (£150,000 + £20,000) ÷ 2, ignoring the unequal probabilities.

Question 9 · Syllabus ref D1a · Limitations of expected value

Which of the following is a recognised limitation of using expected monetary value (EMV) as the sole criterion for decision-making under risk?

  1. EMV is too complicated to calculate for most business decisions
  2. It ignores outcome variance, so risk attitude and extreme losses are not reflected
  3. EMV always produces the same result regardless of probabilities assigned
  4. EMV only applies when there are exactly two possible outcomes
Show answer and explanation

Answer: B. The fundamental limitation of EMV is that it averages outcomes weighted by probability but ignores the spread of those outcomes — a project with the same EMV as another but with a range of outcomes including catastrophic losses would be treated identically, even though a risk-averse manager would rationally prefer the less variable option. Risk attitude, scenario analysis and utility theory are used alongside EMV to address this limitation. EMV calculations are straightforward, not inherently complicated. The probability inputs do affect the result significantly, and EMV can handle any number of outcomes, not just two.

Question 10 · Syllabus ref D1a · Decision tree — rollback worked example

A company can invest £30,000 now. If the market is good (55% probability), it can invest a further £20,000 and earn revenue of £120,000. If the market is poor (45% probability), it earns only £15,000 with no further investment. What is the expected net value of the project, ignoring discounting?

  1. £61,750
  2. £13,250
  3. £31,750
  4. £52,500
Show answer and explanation

Answer: C. Good market outcome: revenue £120,000 − further investment £20,000 = net £100,000 from that branch. Poor market outcome: revenue £15,000, no further investment. Expected value of outcomes = (0.55 × £100,000) + (0.45 × £15,000) = £55,000 + £6,750 = £61,750. Less initial investment £30,000 = expected net value £31,750. The £61,750 figure is the EV before deducting the initial investment. The £13,250 figure might arise from netting incorrectly. The £52,500 figure could come from applying 55% to £120,000 with no deduction for the further investment.

Question 11 · Syllabus ref D1b · Risk response — insurance as transfer

A company takes out professional indemnity insurance against the risk of being sued for negligent advice. Which TARA response does this represent?

  1. Avoid — the company has ceased giving advice to eliminate the risk
  2. Reduce — the company has lowered the likelihood of being sued through better training
  3. Accept — the company has decided to absorb any losses itself without further action
  4. Transfer — the financial consequences of the risk are passed to an insurer in exchange for a premium
Show answer and explanation

Answer: D. Insurance transfers the financial consequences of a risk to a third party (the insurer) in exchange for a premium payment — this is the defining feature of the Transfer risk response in TARA. Avoidance would require the company to stop giving advice altogether. Reduction would involve actions such as improved training or quality control to lower the probability of negligent advice occurring. Acceptance means consciously deciding to retain the risk and bear any resulting loss internally, which is the opposite of paying a premium to transfer it.

Question 12 · Syllabus ref D1b · TARA — reduce vs accept

A company assesses a low-probability risk of a minor IT outage lasting less than 30 minutes. The cost of any mitigation measures would substantially exceed the likely financial impact of the risk. Which TARA response is most appropriate?

  1. Accept — the cost of mitigation outweighs the risk's expected impact, making it rational to accept and absorb the risk
  2. Avoid — the company should cease all IT activities to eliminate the risk
  3. Reduce — all risks must be reduced regardless of the cost of mitigation
  4. Transfer — insurance should be taken out for every possible risk however minor
Show answer and explanation

Answer: A. When the cost of mitigation substantially exceeds the expected impact of a low-probability, low-impact risk, acceptance is the rational TARA response — the organisation consciously decides to absorb the risk rather than spend more than it is worth to mitigate it. Avoidance would be entirely disproportionate for a minor IT outage. Reduce does not mean all risks must be reduced regardless of cost — cost-benefit analysis is central to choosing between risk responses. Taking out insurance for every minor, low-cost risk would create unnecessary expense and is not a principle of good risk management.

Question 13 · Syllabus ref D1c · Big data and risk identification

How can the availability of big data and advanced analytics improve an organisation's risk management process?

  1. By eliminating all uncertainty from business decisions, making traditional risk management unnecessary
  2. By enabling more sophisticated identification of patterns and emerging risks that traditional methods might miss, allowing earlier and better-informed risk responses
  3. By reducing the need for any human risk assessment, since algorithms can fully replace managerial judgement
  4. Big data has no relevant application in risk management processes
Show answer and explanation

Answer: B. Big data and analytics can enhance risk identification by revealing patterns, correlations and emerging signals in large datasets that traditional analytical methods might miss, enabling earlier and better-informed risk responses. They do not eliminate uncertainty — risk management remains necessary precisely because uncertainty persists. Analytics supports human judgement rather than replacing it entirely; interpreting risk patterns and deciding on appropriate responses still requires managerial judgement, context and accountability. Big data has substantial and growing application in risk management across many industries.

Question 14 · Syllabus ref D1d · Ethics — pressure to misstate financial results

A management accountant is pressured by a senior manager to alter a divisional performance report to show a higher profit, against the accountant's professional judgement. What is the appropriate first step for the accountant?

  1. Comply immediately, since following a manager's instruction is always the professional obligation
  2. Alter the figures but add an undisclosed footnote
  3. Refuse and raise the matter through appropriate internal channels such as a more senior manager or audit committee
  4. Resign immediately without first attempting internal resolution
Show answer and explanation

Answer: C. The CIMA Code of Ethics requires professional accountants to maintain integrity and refuse to be party to the preparation of misleading information. The appropriate first response is to decline the request and escalate through appropriate internal channels — such as a more senior manager, internal audit or the audit committee — before considering more drastic action. Complying would be a clear breach of the fundamental principle of integrity. Adding an undisclosed footnote would not make the misleading presentation acceptable. Resigning immediately, before attempting internal resolution, would typically be an extreme last resort rather than the appropriate first step.

Question 15 · Syllabus ref D1a · Decision tree — expected net present value

A company invests £40,000 now. If successful (65% probability), net cash returns of £100,000 are expected. If unsuccessful (35%), net cash returns are £5,000. Ignoring discounting, what is the expected net value of the investment?

  1. £66,750
  2. £26,750
  3. £52,500
  4. £61,750
Show answer and explanation

Answer: B. Expected cash returns = (0.65 × £100,000) + (0.35 × £5,000) = £65,000 + £1,750 = £66,750. Less initial investment £40,000 = expected net value £26,750. The £66,750 figure is the expected return before deducting the investment. The £52,500 might arise from averaging outcomes without using probabilities correctly. The £61,750 misapplies probabilities to the wrong figures.

Question 16 · Syllabus ref D1a · Sensitivity analysis — contribution margin

A project has an NPV of £8,000. The PV of the project's total contribution over its life is £64,000. What is the sensitivity of the NPV to the contribution margin?

  1. 8.0%
  2. 6.25%
  3. 12.5%
  4. 64.0%
Show answer and explanation

Answer: C. Sensitivity = NPV ÷ PV of the variable = £8,000 ÷ £64,000 = 0.125 = 12.5%. This means contribution can fall by 12.5% before the NPV reaches zero — identifying how exposed the project is to a reduction in margin. A common error is to divide £8,000 by £100,000 (8%) if a different base is used, or to confuse the ratio (£64,000 ÷ £8,000 = 8) with the sensitivity percentage. 64.0% reads the £64,000 as a percentage, and 6.25% does not follow from the figures.

Question 17 · Syllabus ref D1c · Information systems — costs and benefits

A company invests in a new management information system. Which of the following correctly identifies a benefit and a cost of this investment?

  1. Benefit: faster, more accurate performance data for decision-making; cost: implementation, training and ongoing licence fees
  2. Benefit: eliminates all business risk; cost: requires replacing all employees with software
  3. Benefit: removes the need for any budgeting process; cost: only occurs once at implementation
  4. Benefit: provides legally guaranteed perfect forecasts; cost: makes financial statements unnecessary
Show answer and explanation

Answer: A. A management information system genuinely provides faster, more accurate data to support decision-making — that is its primary benefit. Its costs include implementation, data migration, training, and ongoing licence or maintenance fees. Information systems do not eliminate business risk, replace all employees, remove the need for budgeting, guarantee perfect forecasts, or make financial statements unnecessary — these reflect a fundamental misunderstanding of what an information system does.

Question 18 · Syllabus ref D1b · Risk appetite and risk response selection

An organisation with a low risk appetite faces a risk with medium probability and high potential impact. Which TARA response is most consistent with a low risk appetite in this situation?

  1. Accept — since a medium probability means the risk is unlikely enough to tolerate
  2. Transfer or Avoid — to eliminate or substantially reduce exposure, given the high potential impact is unacceptable to a risk-averse organisation
  3. Reduce to a minor extent only, since any mitigation is sufficient regardless of residual risk
  4. Ignore, since TARA only applies to high-probability risks
Show answer and explanation

Answer: B. An organisation with a low risk appetite will generally not tolerate high-impact risks even at medium probability — the potential loss is simply too large relative to its risk tolerance. Transfer (e.g. insurance) or Avoidance (eliminating the activity) are therefore the most consistent responses. Acceptance would be more appropriate for a risk-tolerant organisation or a genuinely low-impact risk. Minimal reduction that leaves substantial residual risk is also unlikely to satisfy a risk-averse organisation. TARA applies across the full range of risk probabilities and impacts.

Question 19 · Syllabus ref D1a · Learning curve — cost per unit as output grows

The first unit of a product takes 80 hours. A 75% learning curve applies and labour costs £25 per hour. What is the total labour cost for the first 4 units?

  1. £8,000
  2. £3,000
  3. £4,500
  4. £6,000
Show answer and explanation

Answer: C. 75% learning curve: cumulative average time doubles at 75% of previous. First unit: 80 hours. After 2 units: cumulative average = 80 × 0.75 = 60 hours; total = 2 × 60 = 120 hours. After 4 units: cumulative average = 60 × 0.75 = 45 hours; total = 4 × 45 = 180 hours. Total labour cost for 4 units = 180 × £25 = £4,500. A common error applies no learning: 4 × 80 × £25 = £8,000. Another applies 75% once to total hours: 4 × 80 × 0.75 × £25 = £6,000, incorrectly treating it as a flat reduction. £3,000 is the cost of the first two units only (120 hours × £25).

Question 20 · Syllabus ref D1a · Maximin vs maximax decision criteria

A manager chooses the strategy that minimises the worst possible outcome, regardless of its expected value. Which decision criterion is being applied?

  1. Maximin — selecting the option with the best worst-case outcome, reflecting a risk-averse approach
  2. Maximax — selecting the option with the best best-case outcome, reflecting a risk-seeking approach
  3. Expected monetary value — weighting outcomes by their probability
  4. Minimax regret — minimising the maximum regret across all outcomes
Show answer and explanation

Answer: A. Maximin selects the option whose worst-case outcome is the least damaging — it is a conservative, risk-averse criterion. Maximax is the opposite: it selects the option with the highest possible upside, reflecting a risk-seeking attitude. Expected monetary value uses probability-weighted averages, not worst-case thinking. Minimax regret minimises the maximum difference between the actual outcome and the best outcome that could have been achieved under each scenario — a different concept again.

Question 21 · Syllabus ref D1b · Upside risk — exploiting opportunities

A company identifies that a new regulation is likely to create a significant demand surge for its products. It decides to increase production capacity in advance of the regulation taking effect. Which risk management concept does this illustrate?

  1. Managing downside risk — mitigating the negative consequences of the regulation
  2. Managing upside risk — proactively positioning to exploit a positive uncertainty before it materialises
  3. Risk acceptance — absorbing the consequences of the new regulation without any response
  4. Risk transfer — passing the financial consequences of the regulation to another party
Show answer and explanation

Answer: B. Proactively increasing capacity to benefit from an anticipated demand surge is an example of managing upside risk — recognising positive uncertainty and taking deliberate action to capture the opportunity before it fully materialises. This is the proactive, value-creating side of risk management. It is not downside risk management (there is no adverse consequence being mitigated here), not acceptance (which is passive), and not transfer (which passes consequences to third parties).

Question 22 · Syllabus ref D1c · Big data — opportunities and limitations

Which of the following is a genuine limitation of big data in management decision-making, despite its potential benefits?

  1. Big data eliminates all uncertainty from business decisions, making risk management unnecessary
  2. Big data always leads to better decisions, regardless of the quality of the underlying data
  3. The volume, variety and speed of data can create analytical complexity and data quality challenges that require significant investment to manage effectively
  4. The use of big data requires no human interpretation, since algorithms automatically produce correct conclusions
Show answer and explanation

Answer: C. While big data can provide richer analytical insight, it also creates real challenges: managing large, diverse, fast-moving datasets requires substantial investment in technology, skills and data governance, and data quality problems can undermine analytical outputs ("garbage in, garbage out"). Big data does not eliminate uncertainty — it can reduce it in some areas while creating new uncertainties in others. The quality of underlying data fundamentally affects decision quality, and human interpretation remains essential for contextualising and acting on algorithmic outputs responsibly.

Question 23 · Syllabus ref D1a · EV — limitations for one-off decisions

A company faces a one-off decision to launch a new product. The EMV of launching is positive (£200,000), but the worst-case outcome is a loss of £800,000, which would seriously damage the company. Why might the management team reasonably decide not to launch, despite the positive EMV?

  1. EMV averages repeated scenarios; for a one-off event a risk-averse team may not accept the worst-case loss
  2. A positive EMV guarantees a positive actual outcome for any single decision
  3. The worst-case outcome is irrelevant when EMV is positive
  4. Risk aversion is irrational and should always be overridden by EMV
Show answer and explanation

Answer: A. EMV is most meaningful when a decision is repeated many times, since the average then approximates the expected value. For a one-off decision, the actual outcome is either good or bad — there is no averaging across repetitions. A team that cannot absorb an £800,000 loss may rationally decline to launch even with a positive EMV, since the expected value does not protect them from the possibility of the worst case actually occurring. Risk aversion in one-off, high-stakes decisions is not irrational — it reflects genuine concern about downside exposure that EMV alone does not capture.